ID | Task_Name | Duration | Start_Date | Finish_Date | Predecessors | Resource_Names |
1 | Scope | 3.5 days | Mon 10/7/02 | Thu 10/10/02 | | |
2 | Determine project scope | 4 hrs | Mon 10/7/02 | Mon 10/7/02 | | Management |
3 | Secure project sponsorship | 1 day | Mon 10/7/02 | Tue 10/8/02 | 2 | Management |
4 | Define preliminary resources | 1 day | Tue 10/8/02 | Wed 10/9/02 | 3 | Project Manager |
5 | Secure core resources | 1 day | Wed 10/9/02 | Thu 10/10/02 | 4 | Project Manager |
6 | Scope complete | 0 days | Thu 10/10/02 | Thu 10/10/02 | 5 | |
7 | Analysis/Software Requirements | 8.5 days | Thu 10/10/02 | Tue 10/22/02 | | |
8 | Conduct needs analysis | 2 days | Thu 10/10/02 | Mon 10/14/02 | 6 | Analyst |
9 | Draft preliminary software specifications | 3 days | Mon 10/14/02 | Thu 10/17/02 | 8 | Analyst |
10 | Develop preliminary budget | 2 days | Tue 10/15/02 | Thu 10/17/02 | 9 | Project Manager |
11 | Review software specifications/budget with team | 2 hrs | Wed 10/16/02 | Wed 10/16/02 | 10 | Project Manager,Analyst |
12 | Incorporate feedback on software specifications | 1 day | Wed 10/16/02 | Thu 10/17/02 | 11 | Analyst |
13 | Develop delivery timeline | 2 days | Thu 10/17/02 | Mon 10/21/02 | 12 | Project Manager |
14 | Obtain approvals to proceed (concept, timeline, budget) | 2 hrs | Fri 10/18/02 | Fri 10/18/02 | 13 | Management,Project Manager |
15 | Secure required resources | 2 days | Mon 10/21/02 | Tue 10/22/02 | 14 | Project Manager |
16 | Analysis complete | 0 days | Tue 10/22/02 | Tue 10/22/02 | 15 | |
17 | Design | 12 days | Tue 10/22/02 | Wed 11/6/02 | | |
18 | Review preliminary software specifications | 2 days | Tue 10/22/02 | Wed 10/23/02 | 16 | Analyst |
19 | Develop functional specifications | 5 days | Wed 10/23/02 | Tue 10/29/02 | 18 | Analyst |
20 | Develop prototype based on functional specifications | 4 days | Fri 10/25/02 | Fri 11/1/02 | 19 | Analyst |
21 | Review functional specifications | 2 days | Tue 10/29/02 | Wed 10/30/02 | 20 | Management |
22 | Incorporate feedback into functional specifications | 2 days | Wed 10/30/02 | Thu 10/31/02 | 21 | Management |
23 | Obtain approval to proceed | 5 days | Thu 10/31/02 | Wed 11/6/02 | 22 | Management,Project Manager |
24 | Design complete | 0 days | Wed 11/6/02 | Wed 11/6/02 | 23 | |
25 | Development | 27 days | Thu 11/7/02 | Fri 12/13/02 | | |
26 | Review functional specifications | 4 days | Thu 11/7/02 | Tue 11/12/02 | 24 | Developer |
27 | Identify modular/tiered design parameters | 3 days | Wed 11/13/02 | Fri 11/15/02 | 26 | Developer |
28 | Assign development staff | 1 day | Fri 11/15/02 | Fri 11/15/02 | 27 | Developer |
29 | Develop code | 20 days | Mon 11/18/02 | Fri 12/13/02 | 28 | Developer |
30 | Developer testing (primary debugging) | 15 days | Mon 11/25/02 | Fri 12/13/02 | 29FS-75% | Developer |
31 | Development complete | 0 days | Fri 12/13/02 | Fri 12/13/02 | 30 | |
32 | Testing | 50 days | Thu 11/7/02 | Wed 1/15/03 | | |
33 | Develop unit test plans using product specifications | 1 day | Thu 11/7/02 | Thu 11/7/02 | 24 | Testers |
34 | Develop integration test plans using product specifications | 1 day | Thu 11/7/02 | Thu 11/7/02 | 24 | Testers |
35 | Unit Testing | 11 days | Mon 12/16/02 | Mon 12/30/02 | | |
36 | Review modular code | 2 days | Mon 12/16/02 | Tue 12/17/02 | 33,31 | Testers |
37 | Test component modules to product specifications | 2 days | Wed 12/18/02 | Thu 12/19/02 | 31,36 | Testers |
38 | Identify anomalies to product specifications | 2 days | Fri 12/20/02 | Mon 12/23/02 | 37 | Testers |
39 | Modify code | 3 days | Tue 12/24/02 | Thu 12/26/02 | 38 | Testers |
40 | Re-test modified code | 2 days | Fri 12/27/02 | Mon 12/30/02 | 39 | Testers |
41 | Unit testing complete | 0 days | Mon 12/30/02 | Mon 12/30/02 | 40 | |
42 | Integration Testing | 12 days | Tue 12/31/02 | Wed 1/15/03 | | |
43 | Test module integration | 5 days | Tue 12/31/02 | Mon 1/6/03 | 41 | Testers |
44 | Identify anomalies to specifications | 2 days | Tue 1/7/03 | Wed 1/8/03 | 43 | Testers |
45 | Modify code | 3 days | Thu 1/9/03 | Mon 1/13/03 | 44 | Testers |
46 | Re-test modified code | 2 days | Tue 1/14/03 | Wed 1/15/03 | 45 | Testers |
47 | Integration testing complete | 0 days | Wed 1/15/03 | Wed 1/15/03 | 46 | |
48 | Training | 35 days | Thu 11/7/02 | Wed 12/25/02 | | |
49 | Develop training specifications for end users | 1 day | Thu 11/7/02 | Thu 11/7/02 | 24 | Trainers |
50 | Develop training specifications for helpdesk support staff | 1 day | Thu 11/7/02 | Thu 11/7/02 | 24 | Trainers |
51 | Identify training delivery methodology (computer based training, classroom, etc.) | 1 day | Thu 11/7/02 | Thu 11/7/02 | 24 | Trainers |
52 | Develop training materials | 1 wk | Mon 12/16/02 | Fri 12/20/02 | 49,31,50,51 | Trainers |
53 | Conduct training usability study | 1 day | Mon 12/23/02 | Mon 12/23/02 | 52 | Trainers |
54 | Finalize training materials | 1 day | Tue 12/24/02 | Tue 12/24/02 | 53 | Trainers |
55 | Develop training delivery mechanism | 1 day | Wed 12/25/02 | Wed 12/25/02 | 54 | Trainers |
56 | Training materials complete | 0 days | Wed 12/25/02 | Wed 12/25/02 | 55 | |
57 | Documentation | 37 days | Thu 11/7/02 | Fri 12/27/02 | | |
58 | Develop Help specification | 1 day | Thu 11/7/02 | Thu 11/7/02 | 24 | Technical Communicators |
59 | Develop Help system | 3 wks | Mon 12/2/02 | Fri 12/20/02 | 58,29FS-50% | Technical Communicators |
60 | Review Help documentation | 3 days | Mon 12/23/02 | Wed 12/25/02 | 59 | Technical Communicators |
61 | Incorporate Help documentation feedback | 2 days | Thu 12/26/02 | Fri 12/27/02 | 60 | Technical Communicators |
62 | Develop user manuals specifications | 2 days | Thu 11/7/02 | Fri 11/8/02 | 24 | Technical Communicators |
63 | Develop user manuals | 3 wks | Mon 12/2/02 | Fri 12/20/02 | 62,29FS-50% | Technical Communicators |
64 | Review all user documentation | 2 days | Mon 12/23/02 | Tue 12/24/02 | 63 | Technical Communicators |
65 | Incorporate user documentation feedback | 2 days | Wed 12/25/02 | Thu 12/26/02 | 64 | Technical Communicators |
66 | Documentation complete | 0 days | Fri 12/27/02 | Fri 12/27/02 | 65,61 | |
67 | Pilot | 68 days | Wed 10/23/02 | Fri 1/24/03 | | |
68 | Identify test group | 1 day | Wed 10/23/02 | Wed 10/23/02 | 16 | Project Manager |
69 | Develop software delivery mechanism | 1 day | Thu 10/24/02 | Thu 10/24/02 | 68 | |
70 | Install/deploy software | 1 day | Thu 1/16/03 | Thu 1/16/03 | 47,69,66,56 | Deployment Team |
71 | Obtain user feedback | 1 wk | Fri 1/17/03 | Thu 1/23/03 | 70 | Deployment Team |
72 | Evaluate testing information | 1 day | Fri 1/24/03 | Fri 1/24/03 | 71 | Deployment Team |
73 | Pilot complete | 0 days | Fri 1/24/03 | Fri 1/24/03 | 72 | |
74 | Deployment | 5 days | Mon 1/27/03 | Fri 1/31/03 | | |
75 | Determine final deployment strategy | 1 day | Mon 1/27/03 | Mon 1/27/03 | 73 | Deployment Team |
76 | Develop deployment methodology | 1 day | Tue 1/28/03 | Tue 1/28/03 | 75 | Deployment Team |
77 | Secure deployment resources | 1 day | Wed 1/29/03 | Wed 1/29/03 | 76 | Deployment Team |
78 | Train support staff | 1 day | Thu 1/30/03 | Thu 1/30/03 | 77 | Deployment Team |
79 | Deploy software | 1 day | Fri 1/31/03 | Fri 1/31/03 | 78 | Deployment Team |
80 | Deployment complete | 0 days | Fri 1/31/03 | Fri 1/31/03 | 79 | |
81 | Post Implementation Review | 3 days | Mon 2/3/03 | Wed 2/5/03 | | |
82 | Document lessons learned | 1 day | Mon 2/3/03 | Mon 2/3/03 | 80 | Project Manager |
83 | Distribute to team members | 1 day | Tue 2/4/03 | Tue 2/4/03 | 82 | Project Manager |
84 | Create software maintenance team | 1 day | Wed 2/5/03 | Wed 2/5/03 | 83 | Project Manager |
85 | Post implementation review complete | 0 days | Wed 2/5/03 | Wed 2/5/03 | 84 | |
86 | Software development template complete | 0 days | Wed 2/5/03 | Wed 2/5/03 | 85 | |