Resource Export Table
Home Up Who Does What Baseline Comparison Task Data Resource Export Table Tasks Tasks with Assignments Top Level Tasks

 

WR Software Development


Project Start Date: Sat 10/5/02
Project Finish Date: Wed 2/5/03

Resource_Export_Table

IDUnique_IDResource_NameInitialsMax_UnitsStandard_RateOvertime_RateCost_Per_UseAccrue_AtCostBaseline_CostActual_CostScheduled_WorkBaseline_WorkActual_WorkOvertime_WorkGroup_NameCodeText1Text2Text3Text4Text5Email_Address
11ManagementM100%$0.00/hr$0.00/hr$0.00Prorated$0.00$0.00$0.0086 hrs86 hrs86 hrs0 hrs        
22Project ManagerP100%$0.00/hr$0.00/hr$0.00Prorated$0.00$0.00$0.00140 hrs140 hrs94 hrs0 hrs        
33AnalystA100%$0.00/hr$0.00/hr$0.00Prorated$0.00$0.00$0.00138 hrs138 hrs118 hrs0 hrs        
44DeveloperD100%$0.00/hr$0.00/hr$0.00Prorated$0.00$0.00$0.00344 hrs344 hrs40.4 hrs0 hrs        
55TestersT100%$0.00/hr$0.00/hr$0.00Prorated$0.00$0.00$0.00200 hrs200 hrs0 hrs0 hrs        
66TrainersT100%$0.00/hr$0.00/hr$0.00Prorated$0.00$0.00$0.0088 hrs88 hrs0 hrs0 hrs        
77Technical CommunicatorsT100%$0.00/hr$0.00/hr$0.00Prorated$0.00$0.00$0.00336 hrs336 hrs0 hrs0 hrs        
88Deployment TeamD100%$0.00/hr$0.00/hr$0.00Prorated$0.00$0.00$0.0096 hrs96 hrs0 hrs0 hrs        