Baseline Comparison
Home Up Who Does What Baseline Comparison Task Data Resource Export Table Tasks Tasks with Assignments Top Level Tasks

 

WR Software Development


Project Start Date: Sat 10/5/02
Project Finish Date: Wed 2/5/03

Baseline Comparison

ID
Name
DurationStartFinishWorkCostBaseline DurationBaseline StartBaseline FinishBaseline WorkBaseline CostDuration VarianceWork VarianceCost Variance
1
Scope
3.5 daysMon 10/7/02Thu 10/10/0228 hrs$0.003.5 daysMon 10/7/02Thu 10/10/0228 hrs$0.000 days0 hrs$0.00
2
Determine project scope
4 hrsMon 10/7/02Mon 10/7/024 hrs$0.004 hrsMon 10/7/02Mon 10/7/024 hrs$0.000 hrs0 hrs$0.00
3
Secure project sponsorship
1 dayMon 10/7/02Tue 10/8/028 hrs$0.001 dayMon 10/7/02Tue 10/8/028 hrs$0.000 days0 hrs$0.00
4
Define preliminary resources
1 dayTue 10/8/02Wed 10/9/028 hrs$0.001 dayTue 10/8/02Wed 10/9/028 hrs$0.000 days0 hrs$0.00
5
Secure core resources
1 dayWed 10/9/02Thu 10/10/028 hrs$0.001 dayWed 10/9/02Thu 10/10/028 hrs$0.000 days0 hrs$0.00
6
Scope complete
0 daysThu 10/10/02Thu 10/10/020 hrs$0.000 daysThu 10/10/02Thu 10/10/020 hrs$0.000 days0 hrs$0.00
7
Analysis/Software Requirements
8.5 daysThu 10/10/02Tue 10/22/02104 hrs$0.008.5 daysThu 10/10/02Tue 10/22/02104 hrs$0.000 days0 hrs$0.00
8
Conduct needs analysis
2 daysThu 10/10/02Mon 10/14/0216 hrs$0.002 daysThu 10/10/02Mon 10/14/0216 hrs$0.000 days0 hrs$0.00
9
Draft preliminary software specifications
3 daysMon 10/14/02Thu 10/17/0224 hrs$0.003 daysMon 10/14/02Thu 10/17/0224 hrs$0.000 days0 hrs$0.00
10
Develop preliminary budget
2 daysTue 10/15/02Thu 10/17/0216 hrs$0.002 daysTue 10/15/02Thu 10/17/0216 hrs$0.000 days0 hrs$0.00
11
Review software specifications/budget with team
2 hrsWed 10/16/02Wed 10/16/024 hrs$0.002 hrsWed 10/16/02Wed 10/16/024 hrs$0.000 hrs0 hrs$0.00
12
Incorporate feedback on software specifications
1 dayWed 10/16/02Thu 10/17/028 hrs$0.001 dayWed 10/16/02Thu 10/17/028 hrs$0.000 days0 hrs$0.00
13
Develop delivery timeline
2 daysThu 10/17/02Mon 10/21/0216 hrs$0.002 daysThu 10/17/02Mon 10/21/0216 hrs$0.000 days0 hrs$0.00
14
Obtain approvals to proceed (concept, timeline, budget)
2 hrsFri 10/18/02Fri 10/18/024 hrs$0.002 hrsFri 10/18/02Fri 10/18/024 hrs$0.000 hrs0 hrs$0.00
15
Secure required resources
2 daysMon 10/21/02Tue 10/22/0216 hrs$0.002 daysMon 10/21/02Tue 10/22/0216 hrs$0.000 days0 hrs$0.00
16
Analysis complete
0 daysTue 10/22/02Tue 10/22/020 hrs$0.000 daysTue 10/22/02Tue 10/22/020 hrs$0.000 days0 hrs$0.00
17
Design
12 daysTue 10/22/02Wed 11/6/02200 hrs$0.0012 daysTue 10/22/02Wed 11/6/02200 hrs$0.000 days0 hrs$0.00
18
Review preliminary software specifications
2 daysTue 10/22/02Wed 10/23/0216 hrs$0.002 daysTue 10/22/02Wed 10/23/0216 hrs$0.000 days0 hrs$0.00
19
Develop functional specifications
5 daysWed 10/23/02Tue 10/29/0240 hrs$0.005 daysWed 10/23/02Tue 10/29/0240 hrs$0.000 days0 hrs$0.00
20
Develop prototype based on functional specifications
4 daysFri 10/25/02Fri 11/1/0232 hrs$0.004 daysFri 10/25/02Fri 11/1/0232 hrs$0.000 days0 hrs$0.00
21
Review functional specifications
2 daysTue 10/29/02Wed 10/30/0216 hrs$0.002 daysTue 10/29/02Wed 10/30/0216 hrs$0.000 days0 hrs$0.00
22
Incorporate feedback into functional specifications
2 daysWed 10/30/02Thu 10/31/0216 hrs$0.002 daysWed 10/30/02Thu 10/31/0216 hrs$0.000 days0 hrs$0.00
23
Obtain approval to proceed
5 daysThu 10/31/02Wed 11/6/0280 hrs$0.005 daysThu 10/31/02Wed 11/6/0280 hrs$0.000 days0 hrs$0.00
24
Design complete
0 daysWed 11/6/02Wed 11/6/020 hrs$0.000 daysWed 11/6/02Wed 11/6/020 hrs$0.000 days0 hrs$0.00
25
Development
27 daysThu 11/7/02Fri 12/13/02344 hrs$0.0027 daysThu 11/7/02Fri 12/13/02344 hrs$0.000 days0 hrs$0.00
26
Review functional specifications
4 daysThu 11/7/02Tue 11/12/0232 hrs$0.004 daysThu 11/7/02Tue 11/12/0232 hrs$0.000 days0 hrs$0.00
27
Identify modular/tiered design parameters
3 daysWed 11/13/02Fri 11/15/0224 hrs$0.003 daysWed 11/13/02Fri 11/15/0224 hrs$0.000 days0 hrs$0.00
28
Assign development staff
1 dayFri 11/15/02Fri 11/15/028 hrs$0.001 dayFri 11/15/02Fri 11/15/028 hrs$0.000 days0 hrs$0.00
29
Develop code
20 daysMon 11/18/02Fri 12/13/02160 hrs$0.0020 daysMon 11/18/02Fri 12/13/02160 hrs$0.000 days0 hrs$0.00
30
Developer testing (primary debugging)
15 daysMon 11/25/02Fri 12/13/02120 hrs$0.0015 daysMon 11/25/02Fri 12/13/02120 hrs$0.000 days0 hrs$0.00
31
Development complete
0 daysFri 12/13/02Fri 12/13/020 hrs$0.000 daysFri 12/13/02Fri 12/13/020 hrs$0.000 days0 hrs$0.00
32
Testing
50 daysThu 11/7/02Wed 1/15/03200 hrs$0.0050 daysThu 11/7/02Wed 1/15/03200 hrs$0.000 days0 hrs$0.00
33
Develop unit test plans using product specifications
1 dayThu 11/7/02Thu 11/7/028 hrs$0.001 dayThu 11/7/02Thu 11/7/028 hrs$0.000 days0 hrs$0.00
34
Develop integration test plans using product specifications
1 dayThu 11/7/02Thu 11/7/028 hrs$0.001 dayThu 11/7/02Thu 11/7/028 hrs$0.000 days0 hrs$0.00
35
Unit Testing
11 daysMon 12/16/02Mon 12/30/0288 hrs$0.0011 daysMon 12/16/02Mon 12/30/0288 hrs$0.000 days0 hrs$0.00
36
Review modular code
2 daysMon 12/16/02Tue 12/17/0216 hrs$0.002 daysMon 12/16/02Tue 12/17/0216 hrs$0.000 days0 hrs$0.00
37
Test component modules to product specifications
2 daysWed 12/18/02Thu 12/19/0216 hrs$0.002 daysWed 12/18/02Thu 12/19/0216 hrs$0.000 days0 hrs$0.00
38
Identify anomalies to product specifications
2 daysFri 12/20/02Mon 12/23/0216 hrs$0.002 daysFri 12/20/02Mon 12/23/0216 hrs$0.000 days0 hrs$0.00
39
Modify code
3 daysTue 12/24/02Thu 12/26/0224 hrs$0.003 daysTue 12/24/02Thu 12/26/0224 hrs$0.000 days0 hrs$0.00
40
Re-test modified code
2 daysFri 12/27/02Mon 12/30/0216 hrs$0.002 daysFri 12/27/02Mon 12/30/0216 hrs$0.000 days0 hrs$0.00
41
Unit testing complete
0 daysMon 12/30/02Mon 12/30/020 hrs$0.000 daysMon 12/30/02Mon 12/30/020 hrs$0.000 days0 hrs$0.00
42
Integration Testing
12 daysTue 12/31/02Wed 1/15/0396 hrs$0.0012 daysTue 12/31/02Wed 1/15/0396 hrs$0.000 days0 hrs$0.00
43
Test module integration
5 daysTue 12/31/02Mon 1/6/0340 hrs$0.005 daysTue 12/31/02Mon 1/6/0340 hrs$0.000 days0 hrs$0.00
44
Identify anomalies to specifications
2 daysTue 1/7/03Wed 1/8/0316 hrs$0.002 daysTue 1/7/03Wed 1/8/0316 hrs$0.000 days0 hrs$0.00
45
Modify code
3 daysThu 1/9/03Mon 1/13/0324 hrs$0.003 daysThu 1/9/03Mon 1/13/0324 hrs$0.000 days0 hrs$0.00
46
Re-test modified code
2 daysTue 1/14/03Wed 1/15/0316 hrs$0.002 daysTue 1/14/03Wed 1/15/0316 hrs$0.000 days0 hrs$0.00
47
Integration testing complete
0 daysWed 1/15/03Wed 1/15/030 hrs$0.000 daysWed 1/15/03Wed 1/15/030 hrs$0.000 days0 hrs$0.00
48
Training
35 daysThu 11/7/02Wed 12/25/0288 hrs$0.0035 daysThu 11/7/02Wed 12/25/0288 hrs$0.000 days0 hrs$0.00
49
Develop training specifications for end users
1 dayThu 11/7/02Thu 11/7/028 hrs$0.001 dayThu 11/7/02Thu 11/7/028 hrs$0.000 days0 hrs$0.00
50
Develop training specifications for helpdesk support staff
1 dayThu 11/7/02Thu 11/7/028 hrs$0.001 dayThu 11/7/02Thu 11/7/028 hrs$0.000 days0 hrs$0.00
51
Identify training delivery methodology (computer based training, classroom, etc.)
1 dayThu 11/7/02Thu 11/7/028 hrs$0.001 dayThu 11/7/02Thu 11/7/028 hrs$0.000 days0 hrs$0.00
52
Develop training materials
1 wkMon 12/16/02Fri 12/20/0240 hrs$0.001 wkMon 12/16/02Fri 12/20/0240 hrs$0.000 wks0 hrs$0.00
53
Conduct training usability study
1 dayMon 12/23/02Mon 12/23/028 hrs$0.001 dayMon 12/23/02Mon 12/23/028 hrs$0.000 days0 hrs$0.00
54
Finalize training materials
1 dayTue 12/24/02Tue 12/24/028 hrs$0.001 dayTue 12/24/02Tue 12/24/028 hrs$0.000 days0 hrs$0.00
55
Develop training delivery mechanism
1 dayWed 12/25/02Wed 12/25/028 hrs$0.001 dayWed 12/25/02Wed 12/25/028 hrs$0.000 days0 hrs$0.00
56
Training materials complete
0 daysWed 12/25/02Wed 12/25/020 hrs$0.000 daysWed 12/25/02Wed 12/25/020 hrs$0.000 days0 hrs$0.00
57
Documentation
37 daysThu 11/7/02Fri 12/27/02336 hrs$0.0037 daysThu 11/7/02Fri 12/27/02336 hrs$0.000 days0 hrs$0.00
58
Develop Help specification
1 dayThu 11/7/02Thu 11/7/028 hrs$0.001 dayThu 11/7/02Thu 11/7/028 hrs$0.000 days0 hrs$0.00
59
Develop Help system
3 wksMon 12/2/02Fri 12/20/02120 hrs$0.003 wksMon 12/2/02Fri 12/20/02120 hrs$0.000 wks0 hrs$0.00
60
Review Help documentation
3 daysMon 12/23/02Wed 12/25/0224 hrs$0.003 daysMon 12/23/02Wed 12/25/0224 hrs$0.000 days0 hrs$0.00
61
Incorporate Help documentation feedback
2 daysThu 12/26/02Fri 12/27/0216 hrs$0.002 daysThu 12/26/02Fri 12/27/0216 hrs$0.000 days0 hrs$0.00
62
Develop user manuals specifications
2 daysThu 11/7/02Fri 11/8/0216 hrs$0.002 daysThu 11/7/02Fri 11/8/0216 hrs$0.000 days0 hrs$0.00
63
Develop user manuals
3 wksMon 12/2/02Fri 12/20/02120 hrs$0.003 wksMon 12/2/02Fri 12/20/02120 hrs$0.000 wks0 hrs$0.00
64
Review all user documentation
2 daysMon 12/23/02Tue 12/24/0216 hrs$0.002 daysMon 12/23/02Tue 12/24/0216 hrs$0.000 days0 hrs$0.00
65
Incorporate user documentation feedback
2 daysWed 12/25/02Thu 12/26/0216 hrs$0.002 daysWed 12/25/02Thu 12/26/0216 hrs$0.000 days0 hrs$0.00
66
Documentation complete
0 daysFri 12/27/02Fri 12/27/020 hrs$0.000 daysFri 12/27/02Fri 12/27/020 hrs$0.000 days0 hrs$0.00
67
Pilot
68 daysWed 10/23/02Fri 1/24/0364 hrs$0.0068 daysWed 10/23/02Fri 1/24/0364 hrs$0.000 days0 hrs$0.00
68
Identify test group
1 dayWed 10/23/02Wed 10/23/028 hrs$0.001 dayWed 10/23/02Wed 10/23/028 hrs$0.000 days0 hrs$0.00
69
Develop software delivery mechanism
1 dayThu 10/24/02Thu 10/24/020 hrs$0.001 dayThu 10/24/02Thu 10/24/020 hrs$0.000 days0 hrs$0.00
70
Install/deploy software
1 dayThu 1/16/03Thu 1/16/038 hrs$0.001 dayThu 1/16/03Thu 1/16/038 hrs$0.000 days0 hrs$0.00
71
Obtain user feedback
1 wkFri 1/17/03Thu 1/23/0340 hrs$0.001 wkFri 1/17/03Thu 1/23/0340 hrs$0.000 wks0 hrs$0.00
72
Evaluate testing information
1 dayFri 1/24/03Fri 1/24/038 hrs$0.001 dayFri 1/24/03Fri 1/24/038 hrs$0.000 days0 hrs$0.00
73
Pilot complete
0 daysFri 1/24/03Fri 1/24/030 hrs$0.000 daysFri 1/24/03Fri 1/24/030 hrs$0.000 days0 hrs$0.00
74
Deployment
5 daysMon 1/27/03Fri 1/31/0340 hrs$0.005 daysMon 1/27/03Fri 1/31/0340 hrs$0.000 days0 hrs$0.00
75
Determine final deployment strategy
1 dayMon 1/27/03Mon 1/27/038 hrs$0.001 dayMon 1/27/03Mon 1/27/038 hrs$0.000 days0 hrs$0.00
76
Develop deployment methodology
1 dayTue 1/28/03Tue 1/28/038 hrs$0.001 dayTue 1/28/03Tue 1/28/038 hrs$0.000 days0 hrs$0.00
77
Secure deployment resources
1 dayWed 1/29/03Wed 1/29/038 hrs$0.001 dayWed 1/29/03Wed 1/29/038 hrs$0.000 days0 hrs$0.00
78
Train support staff
1 dayThu 1/30/03Thu 1/30/038 hrs$0.001 dayThu 1/30/03Thu 1/30/038 hrs$0.000 days0 hrs$0.00
79
Deploy software
1 dayFri 1/31/03Fri 1/31/038 hrs$0.001 dayFri 1/31/03Fri 1/31/038 hrs$0.000 days0 hrs$0.00
80
Deployment complete
0 daysFri 1/31/03Fri 1/31/030 hrs$0.000 daysFri 1/31/03Fri 1/31/030 hrs$0.000 days0 hrs$0.00
81
Post Implementation Review
3 daysMon 2/3/03Wed 2/5/0324 hrs$0.003 daysMon 2/3/03Wed 2/5/0324 hrs$0.000 days0 hrs$0.00
82
Document lessons learned
1 dayMon 2/3/03Mon 2/3/038 hrs$0.001 dayMon 2/3/03Mon 2/3/038 hrs$0.000 days0 hrs$0.00
83
Distribute to team members
1 dayTue 2/4/03Tue 2/4/038 hrs$0.001 dayTue 2/4/03Tue 2/4/038 hrs$0.000 days0 hrs$0.00
84
Create software maintenance team
1 dayWed 2/5/03Wed 2/5/038 hrs$0.001 dayWed 2/5/03Wed 2/5/038 hrs$0.000 days0 hrs$0.00
85
Post implementation review complete
0 daysWed 2/5/03Wed 2/5/030 hrs$0.000 daysWed 2/5/03Wed 2/5/030 hrs$0.000 days0 hrs$0.00
86
Software development template complete
0 daysWed 2/5/03Wed 2/5/030 hrs$0.000 daysWed 2/5/03Wed 2/5/030 hrs$0.000 days0 hrs$0.00