Task Data
Home Up Who Does What Baseline Comparison Task Data Resource Export Table Tasks Tasks with Assignments Top Level Tasks

 

WR Software Development


Project Start Date: Sat 10/5/02
Project Finish Date: Wed 2/5/03

Task Data

ID
Task_Name
DurationStart_DateFinish_DatePredecessorsResource_Names
1
Scope
3.5 daysMon 10/7/02Thu 10/10/02  
2
Determine project scope
4 hrsMon 10/7/02Mon 10/7/02 Management
3
Secure project sponsorship
1 dayMon 10/7/02Tue 10/8/022Management
4
Define preliminary resources
1 dayTue 10/8/02Wed 10/9/023Project Manager
5
Secure core resources
1 dayWed 10/9/02Thu 10/10/024Project Manager
6
Scope complete
0 daysThu 10/10/02Thu 10/10/025 
7
Analysis/Software Requirements
8.5 daysThu 10/10/02Tue 10/22/02  
8
Conduct needs analysis
2 daysThu 10/10/02Mon 10/14/026Analyst
9
Draft preliminary software specifications
3 daysMon 10/14/02Thu 10/17/028Analyst
10
Develop preliminary budget
2 daysTue 10/15/02Thu 10/17/029Project Manager
11
Review software specifications/budget with team
2 hrsWed 10/16/02Wed 10/16/0210Project Manager,Analyst
12
Incorporate feedback on software specifications
1 dayWed 10/16/02Thu 10/17/0211Analyst
13
Develop delivery timeline
2 daysThu 10/17/02Mon 10/21/0212Project Manager
14
Obtain approvals to proceed (concept, timeline, budget)
2 hrsFri 10/18/02Fri 10/18/0213Management,Project Manager
15
Secure required resources
2 daysMon 10/21/02Tue 10/22/0214Project Manager
16
Analysis complete
0 daysTue 10/22/02Tue 10/22/0215 
17
Design
12 daysTue 10/22/02Wed 11/6/02  
18
Review preliminary software specifications
2 daysTue 10/22/02Wed 10/23/0216Analyst
19
Develop functional specifications
5 daysWed 10/23/02Tue 10/29/0218Analyst
20
Develop prototype based on functional specifications
4 daysFri 10/25/02Fri 11/1/0219Analyst
21
Review functional specifications
2 daysTue 10/29/02Wed 10/30/0220Management
22
Incorporate feedback into functional specifications
2 daysWed 10/30/02Thu 10/31/0221Management
23
Obtain approval to proceed
5 daysThu 10/31/02Wed 11/6/0222Management,Project Manager
24
Design complete
0 daysWed 11/6/02Wed 11/6/0223 
25
Development
27 daysThu 11/7/02Fri 12/13/02  
26
Review functional specifications
4 daysThu 11/7/02Tue 11/12/0224Developer
27
Identify modular/tiered design parameters
3 daysWed 11/13/02Fri 11/15/0226Developer
28
Assign development staff
1 dayFri 11/15/02Fri 11/15/0227Developer
29
Develop code
20 daysMon 11/18/02Fri 12/13/0228Developer
30
Developer testing (primary debugging)
15 daysMon 11/25/02Fri 12/13/0229FS-75%Developer
31
Development complete
0 daysFri 12/13/02Fri 12/13/0230 
32
Testing
50 daysThu 11/7/02Wed 1/15/03  
33
Develop unit test plans using product specifications
1 dayThu 11/7/02Thu 11/7/0224Testers
34
Develop integration test plans using product specifications
1 dayThu 11/7/02Thu 11/7/0224Testers
35
Unit Testing
11 daysMon 12/16/02Mon 12/30/02  
36
Review modular code
2 daysMon 12/16/02Tue 12/17/0233,31Testers
37
Test component modules to product specifications
2 daysWed 12/18/02Thu 12/19/0231,36Testers
38
Identify anomalies to product specifications
2 daysFri 12/20/02Mon 12/23/0237Testers
39
Modify code
3 daysTue 12/24/02Thu 12/26/0238Testers
40
Re-test modified code
2 daysFri 12/27/02Mon 12/30/0239Testers
41
Unit testing complete
0 daysMon 12/30/02Mon 12/30/0240 
42
Integration Testing
12 daysTue 12/31/02Wed 1/15/03  
43
Test module integration
5 daysTue 12/31/02Mon 1/6/0341Testers
44
Identify anomalies to specifications
2 daysTue 1/7/03Wed 1/8/0343Testers
45
Modify code
3 daysThu 1/9/03Mon 1/13/0344Testers
46
Re-test modified code
2 daysTue 1/14/03Wed 1/15/0345Testers
47
Integration testing complete
0 daysWed 1/15/03Wed 1/15/0346 
48
Training
35 daysThu 11/7/02Wed 12/25/02  
49
Develop training specifications for end users
1 dayThu 11/7/02Thu 11/7/0224Trainers
50
Develop training specifications for helpdesk support staff
1 dayThu 11/7/02Thu 11/7/0224Trainers
51
Identify training delivery methodology (computer based training, classroom, etc.)
1 dayThu 11/7/02Thu 11/7/0224Trainers
52
Develop training materials
1 wkMon 12/16/02Fri 12/20/0249,31,50,51Trainers
53
Conduct training usability study
1 dayMon 12/23/02Mon 12/23/0252Trainers
54
Finalize training materials
1 dayTue 12/24/02Tue 12/24/0253Trainers
55
Develop training delivery mechanism
1 dayWed 12/25/02Wed 12/25/0254Trainers
56
Training materials complete
0 daysWed 12/25/02Wed 12/25/0255 
57
Documentation
37 daysThu 11/7/02Fri 12/27/02  
58
Develop Help specification
1 dayThu 11/7/02Thu 11/7/0224Technical Communicators
59
Develop Help system
3 wksMon 12/2/02Fri 12/20/0258,29FS-50%Technical Communicators
60
Review Help documentation
3 daysMon 12/23/02Wed 12/25/0259Technical Communicators
61
Incorporate Help documentation feedback
2 daysThu 12/26/02Fri 12/27/0260Technical Communicators
62
Develop user manuals specifications
2 daysThu 11/7/02Fri 11/8/0224Technical Communicators
63
Develop user manuals
3 wksMon 12/2/02Fri 12/20/0262,29FS-50%Technical Communicators
64
Review all user documentation
2 daysMon 12/23/02Tue 12/24/0263Technical Communicators
65
Incorporate user documentation feedback
2 daysWed 12/25/02Thu 12/26/0264Technical Communicators
66
Documentation complete
0 daysFri 12/27/02Fri 12/27/0265,61 
67
Pilot
68 daysWed 10/23/02Fri 1/24/03  
68
Identify test group
1 dayWed 10/23/02Wed 10/23/0216Project Manager
69
Develop software delivery mechanism
1 dayThu 10/24/02Thu 10/24/0268 
70
Install/deploy software
1 dayThu 1/16/03Thu 1/16/0347,69,66,56Deployment Team
71
Obtain user feedback
1 wkFri 1/17/03Thu 1/23/0370Deployment Team
72
Evaluate testing information
1 dayFri 1/24/03Fri 1/24/0371Deployment Team
73
Pilot complete
0 daysFri 1/24/03Fri 1/24/0372 
74
Deployment
5 daysMon 1/27/03Fri 1/31/03  
75
Determine final deployment strategy
1 dayMon 1/27/03Mon 1/27/0373Deployment Team
76
Develop deployment methodology
1 dayTue 1/28/03Tue 1/28/0375Deployment Team
77
Secure deployment resources
1 dayWed 1/29/03Wed 1/29/0376Deployment Team
78
Train support staff
1 dayThu 1/30/03Thu 1/30/0377Deployment Team
79
Deploy software
1 dayFri 1/31/03Fri 1/31/0378Deployment Team
80
Deployment complete
0 daysFri 1/31/03Fri 1/31/0379 
81
Post Implementation Review
3 daysMon 2/3/03Wed 2/5/03  
82
Document lessons learned
1 dayMon 2/3/03Mon 2/3/0380Project Manager
83
Distribute to team members
1 dayTue 2/4/03Tue 2/4/0382Project Manager
84
Create software maintenance team
1 dayWed 2/5/03Wed 2/5/0383Project Manager
85
Post implementation review complete
0 daysWed 2/5/03Wed 2/5/0384 
86
Software development template complete
0 daysWed 2/5/03Wed 2/5/0385 