Top Level Tasks
Home Up Who Does What Baseline Comparison Task Data Resource Export Table Tasks Tasks with Assignments Top Level Tasks

 

WR Software Development


Project Start Date: Sat 10/5/02
Project Finish Date: Wed 2/5/03

Top Level Tasks

ID
Task Name
DurationStartFinish% CompleteCostWork
1
Scope
3.5 daysMon 10/7/02Thu 10/10/02100%$0.0028 hrs
7
Analysis/Software Requirements
8.5 daysThu 10/10/02Tue 10/22/0286%$0.00104 hrs
17
Design
12 daysTue 10/22/02Wed 11/6/0288%$0.00200 hrs
25
Development
27 daysThu 11/7/02Fri 12/13/0212%$0.00344 hrs
32
Testing
50 daysThu 11/7/02Wed 1/15/030%$0.00200 hrs
48
Training
35 daysThu 11/7/02Wed 12/25/020%$0.0088 hrs
57
Documentation
37 daysThu 11/7/02Fri 12/27/020%$0.00336 hrs
67
Pilot
68 daysWed 10/23/02Fri 1/24/030%$0.0064 hrs
74
Deployment
5 daysMon 1/27/03Fri 1/31/030%$0.0040 hrs
81
Post Implementation Review
3 daysMon 2/3/03Wed 2/5/030%$0.0024 hrs
86
Software development template complete
0 daysWed 2/5/03Wed 2/5/030%$0.000 hrs