Resources and Assignments | Start | Finish | Work |
Unassigned | Thu 10/10/02 | Wed 2/5/03 | 0 hrs |
Scope complete | Thu 10/10/02 | Thu 10/10/02 | 0 hrs |
Analysis complete | Tue 10/22/02 | Tue 10/22/02 | 0 hrs |
Design complete | Wed 11/6/02 | Wed 11/6/02 | 0 hrs |
Development complete | Fri 12/13/02 | Fri 12/13/02 | 0 hrs |
Unit testing complete | Mon 12/30/02 | Mon 12/30/02 | 0 hrs |
Integration testing complete | Wed 1/15/03 | Wed 1/15/03 | 0 hrs |
Training materials complete | Wed 12/25/02 | Wed 12/25/02 | 0 hrs |
Documentation complete | Fri 12/27/02 | Fri 12/27/02 | 0 hrs |
Develop software delivery mechanism | Thu 10/24/02 | Thu 10/24/02 | 0 hrs |
Pilot complete | Fri 1/24/03 | Fri 1/24/03 | 0 hrs |
Deployment complete | Fri 1/31/03 | Fri 1/31/03 | 0 hrs |
Post implementation review complete | Wed 2/5/03 | Wed 2/5/03 | 0 hrs |
Software development template complete | Wed 2/5/03 | Wed 2/5/03 | 0 hrs |
Management | Mon 10/7/02 | Wed 11/6/02 | 86 hrs |
Determine project scope | Mon 10/7/02 | Mon 10/7/02 | 4 hrs |
Secure project sponsorship | Mon 10/7/02 | Tue 10/8/02 | 8 hrs |
Obtain approvals to proceed (concept, timeline, budget) | Fri 10/18/02 | Fri 10/18/02 | 2 hrs |
Review functional specifications | Tue 10/29/02 | Wed 10/30/02 | 16 hrs |
Incorporate feedback into functional specifications | Wed 10/30/02 | Thu 10/31/02 | 16 hrs |
Obtain approval to proceed | Thu 10/31/02 | Wed 11/6/02 | 40 hrs |
Project Manager | Tue 10/8/02 | Wed 2/5/03 | 140 hrs |
Define preliminary resources | Tue 10/8/02 | Wed 10/9/02 | 8 hrs |
Secure core resources | Wed 10/9/02 | Thu 10/10/02 | 8 hrs |
Develop preliminary budget | Tue 10/15/02 | Thu 10/17/02 | 16 hrs |
Review software specifications/budget with team | Wed 10/16/02 | Wed 10/16/02 | 2 hrs |
Develop delivery timeline | Thu 10/17/02 | Mon 10/21/02 | 16 hrs |
Obtain approvals to proceed (concept, timeline, budget) | Fri 10/18/02 | Fri 10/18/02 | 2 hrs |
Secure required resources | Mon 10/21/02 | Tue 10/22/02 | 16 hrs |
Obtain approval to proceed | Thu 10/31/02 | Wed 11/6/02 | 40 hrs |
Identify test group | Wed 10/23/02 | Wed 10/23/02 | 8 hrs |
Document lessons learned | Mon 2/3/03 | Mon 2/3/03 | 8 hrs |
Distribute to team members | Tue 2/4/03 | Tue 2/4/03 | 8 hrs |
Create software maintenance team | Wed 2/5/03 | Wed 2/5/03 | 8 hrs |
Analyst | Thu 10/10/02 | Fri 11/1/02 | 138 hrs |
Conduct needs analysis | Thu 10/10/02 | Mon 10/14/02 | 16 hrs |
Draft preliminary software specifications | Mon 10/14/02 | Thu 10/17/02 | 24 hrs |
Review software specifications/budget with team | Wed 10/16/02 | Wed 10/16/02 | 2 hrs |
Incorporate feedback on software specifications | Wed 10/16/02 | Thu 10/17/02 | 8 hrs |
Review preliminary software specifications | Tue 10/22/02 | Wed 10/23/02 | 16 hrs |
Develop functional specifications | Wed 10/23/02 | Tue 10/29/02 | 40 hrs |
Develop prototype based on functional specifications | Fri 10/25/02 | Fri 11/1/02 | 32 hrs |
Developer | Thu 11/7/02 | Fri 12/13/02 | 344 hrs |
Review functional specifications | Thu 11/7/02 | Tue 11/12/02 | 32 hrs |
Identify modular/tiered design parameters | Wed 11/13/02 | Fri 11/15/02 | 24 hrs |
Assign development staff | Fri 11/15/02 | Fri 11/15/02 | 8 hrs |
Develop code | Mon 11/18/02 | Fri 12/13/02 | 160 hrs |
Developer testing (primary debugging) | Mon 11/25/02 | Fri 12/13/02 | 120 hrs |
Testers | Thu 11/7/02 | Wed 1/15/03 | 200 hrs |
Develop unit test plans using product specifications | Thu 11/7/02 | Thu 11/7/02 | 8 hrs |
Develop integration test plans using product specifications | Thu 11/7/02 | Thu 11/7/02 | 8 hrs |
Review modular code | Mon 12/16/02 | Tue 12/17/02 | 16 hrs |
Test component modules to product specifications | Wed 12/18/02 | Thu 12/19/02 | 16 hrs |
Identify anomalies to product specifications | Fri 12/20/02 | Mon 12/23/02 | 16 hrs |
Modify code | Tue 12/24/02 | Thu 12/26/02 | 24 hrs |
Re-test modified code | Fri 12/27/02 | Mon 12/30/02 | 16 hrs |
Test module integration | Tue 12/31/02 | Mon 1/6/03 | 40 hrs |
Identify anomalies to specifications | Tue 1/7/03 | Wed 1/8/03 | 16 hrs |
Modify code | Thu 1/9/03 | Mon 1/13/03 | 24 hrs |
Re-test modified code | Tue 1/14/03 | Wed 1/15/03 | 16 hrs |
Trainers | Thu 11/7/02 | Wed 12/25/02 | 88 hrs |
Develop training specifications for end users | Thu 11/7/02 | Thu 11/7/02 | 8 hrs |
Develop training specifications for helpdesk support staff | Thu 11/7/02 | Thu 11/7/02 | 8 hrs |
Identify training delivery methodology (computer based training, classroom, etc.) | Thu 11/7/02 | Thu 11/7/02 | 8 hrs |
Develop training materials | Mon 12/16/02 | Fri 12/20/02 | 40 hrs |
Conduct training usability study | Mon 12/23/02 | Mon 12/23/02 | 8 hrs |
Finalize training materials | Tue 12/24/02 | Tue 12/24/02 | 8 hrs |
Develop training delivery mechanism | Wed 12/25/02 | Wed 12/25/02 | 8 hrs |
Technical Communicators | Thu 11/7/02 | Fri 12/27/02 | 336 hrs |
Develop Help specification | Thu 11/7/02 | Thu 11/7/02 | 8 hrs |
Develop Help system | Mon 12/2/02 | Fri 12/20/02 | 120 hrs |
Review Help documentation | Mon 12/23/02 | Wed 12/25/02 | 24 hrs |
Incorporate Help documentation feedback | Thu 12/26/02 | Fri 12/27/02 | 16 hrs |
Develop user manuals specifications | Thu 11/7/02 | Fri 11/8/02 | 16 hrs |
Develop user manuals | Mon 12/2/02 | Fri 12/20/02 | 120 hrs |
Review all user documentation | Mon 12/23/02 | Tue 12/24/02 | 16 hrs |
Incorporate user documentation feedback | Wed 12/25/02 | Thu 12/26/02 | 16 hrs |
Deployment Team | Thu 1/16/03 | Fri 1/31/03 | 96 hrs |
Install/deploy software | Thu 1/16/03 | Thu 1/16/03 | 8 hrs |
Obtain user feedback | Fri 1/17/03 | Thu 1/23/03 | 40 hrs |
Evaluate testing information | Fri 1/24/03 | Fri 1/24/03 | 8 hrs |
Determine final deployment strategy | Mon 1/27/03 | Mon 1/27/03 | 8 hrs |
Develop deployment methodology | Tue 1/28/03 | Tue 1/28/03 | 8 hrs |
Secure deployment resources | Wed 1/29/03 | Wed 1/29/03 | 8 hrs |
Train support staff | Thu 1/30/03 | Thu 1/30/03 | 8 hrs |
Deploy software | Fri 1/31/03 | Fri 1/31/03 | 8 hrs |