Resource Group | Resource Name | Task Name | Duration | Start | Finish | Cost |
| | Scope | 3.5 days | Mon 10/7/02 | Thu 10/10/02 | $0.00 |
| Management | Determine project scope | 4 hrs | Mon 10/7/02 | Mon 10/7/02 | $0.00 |
| Management | Secure project sponsorship | 1 day | Mon 10/7/02 | Tue 10/8/02 | $0.00 |
| Project Manager | Define preliminary resources | 1 day | Tue 10/8/02 | Wed 10/9/02 | $0.00 |
| Project Manager | Secure core resources | 1 day | Wed 10/9/02 | Thu 10/10/02 | $0.00 |
| | Scope complete | 0 days | Thu 10/10/02 | Thu 10/10/02 | $0.00 |
| | Analysis/Software Requirements | 8.5 days | Thu 10/10/02 | Tue 10/22/02 | $0.00 |
| Analyst | Conduct needs analysis | 2 days | Thu 10/10/02 | Mon 10/14/02 | $0.00 |
| Analyst | Draft preliminary software specifications | 3 days | Mon 10/14/02 | Thu 10/17/02 | $0.00 |
| Project Manager | Develop preliminary budget | 2 days | Tue 10/15/02 | Thu 10/17/02 | $0.00 |
| Project Manager,Analyst | Review software specifications/budget with team | 2 hrs | Wed 10/16/02 | Wed 10/16/02 | $0.00 |
| Analyst | Incorporate feedback on software specifications | 1 day | Wed 10/16/02 | Thu 10/17/02 | $0.00 |
| Project Manager | Develop delivery timeline | 2 days | Thu 10/17/02 | Mon 10/21/02 | $0.00 |
| Management,Project Manager | Obtain approvals to proceed (concept, timeline, budget) | 2 hrs | Fri 10/18/02 | Fri 10/18/02 | $0.00 |
| Project Manager | Secure required resources | 2 days | Mon 10/21/02 | Tue 10/22/02 | $0.00 |
| | Analysis complete | 0 days | Tue 10/22/02 | Tue 10/22/02 | $0.00 |
| | Design | 12 days | Tue 10/22/02 | Wed 11/6/02 | $0.00 |
| Analyst | Review preliminary software specifications | 2 days | Tue 10/22/02 | Wed 10/23/02 | $0.00 |
| Analyst | Develop functional specifications | 5 days | Wed 10/23/02 | Tue 10/29/02 | $0.00 |
| Analyst | Develop prototype based on functional specifications | 4 days | Fri 10/25/02 | Fri 11/1/02 | $0.00 |
| Management | Review functional specifications | 2 days | Tue 10/29/02 | Wed 10/30/02 | $0.00 |
| Management | Incorporate feedback into functional specifications | 2 days | Wed 10/30/02 | Thu 10/31/02 | $0.00 |
| Management,Project Manager | Obtain approval to proceed | 5 days | Thu 10/31/02 | Wed 11/6/02 | $0.00 |
| | Design complete | 0 days | Wed 11/6/02 | Wed 11/6/02 | $0.00 |
| | Development | 27 days | Thu 11/7/02 | Fri 12/13/02 | $0.00 |
| Developer | Review functional specifications | 4 days | Thu 11/7/02 | Tue 11/12/02 | $0.00 |
| Developer | Identify modular/tiered design parameters | 3 days | Wed 11/13/02 | Fri 11/15/02 | $0.00 |
| Developer | Assign development staff | 1 day | Fri 11/15/02 | Fri 11/15/02 | $0.00 |
| Developer | Develop code | 20 days | Mon 11/18/02 | Fri 12/13/02 | $0.00 |
| Developer | Developer testing (primary debugging) | 15 days | Mon 11/25/02 | Fri 12/13/02 | $0.00 |
| | Development complete | 0 days | Fri 12/13/02 | Fri 12/13/02 | $0.00 |
| | Testing | 50 days | Thu 11/7/02 | Wed 1/15/03 | $0.00 |
| Testers | Develop unit test plans using product specifications | 1 day | Thu 11/7/02 | Thu 11/7/02 | $0.00 |
| Testers | Develop integration test plans using product specifications | 1 day | Thu 11/7/02 | Thu 11/7/02 | $0.00 |
| | Unit Testing | 11 days | Mon 12/16/02 | Mon 12/30/02 | $0.00 |
| Testers | Review modular code | 2 days | Mon 12/16/02 | Tue 12/17/02 | $0.00 |
| Testers | Test component modules to product specifications | 2 days | Wed 12/18/02 | Thu 12/19/02 | $0.00 |
| Testers | Identify anomalies to product specifications | 2 days | Fri 12/20/02 | Mon 12/23/02 | $0.00 |
| Testers | Modify code | 3 days | Tue 12/24/02 | Thu 12/26/02 | $0.00 |
| Testers | Re-test modified code | 2 days | Fri 12/27/02 | Mon 12/30/02 | $0.00 |
| | Unit testing complete | 0 days | Mon 12/30/02 | Mon 12/30/02 | $0.00 |
| | Integration Testing | 12 days | Tue 12/31/02 | Wed 1/15/03 | $0.00 |
| Testers | Test module integration | 5 days | Tue 12/31/02 | Mon 1/6/03 | $0.00 |
| Testers | Identify anomalies to specifications | 2 days | Tue 1/7/03 | Wed 1/8/03 | $0.00 |
| Testers | Modify code | 3 days | Thu 1/9/03 | Mon 1/13/03 | $0.00 |
| Testers | Re-test modified code | 2 days | Tue 1/14/03 | Wed 1/15/03 | $0.00 |
| | Integration testing complete | 0 days | Wed 1/15/03 | Wed 1/15/03 | $0.00 |
| | Training | 35 days | Thu 11/7/02 | Wed 12/25/02 | $0.00 |
| Trainers | Develop training specifications for end users | 1 day | Thu 11/7/02 | Thu 11/7/02 | $0.00 |
| Trainers | Develop training specifications for helpdesk support staff | 1 day | Thu 11/7/02 | Thu 11/7/02 | $0.00 |
| Trainers | Identify training delivery methodology (computer based training, classroom, etc.) | 1 day | Thu 11/7/02 | Thu 11/7/02 | $0.00 |
| Trainers | Develop training materials | 1 wk | Mon 12/16/02 | Fri 12/20/02 | $0.00 |
| Trainers | Conduct training usability study | 1 day | Mon 12/23/02 | Mon 12/23/02 | $0.00 |
| Trainers | Finalize training materials | 1 day | Tue 12/24/02 | Tue 12/24/02 | $0.00 |
| Trainers | Develop training delivery mechanism | 1 day | Wed 12/25/02 | Wed 12/25/02 | $0.00 |
| | Training materials complete | 0 days | Wed 12/25/02 | Wed 12/25/02 | $0.00 |
| | Documentation | 37 days | Thu 11/7/02 | Fri 12/27/02 | $0.00 |
| Technical Communicators | Develop Help specification | 1 day | Thu 11/7/02 | Thu 11/7/02 | $0.00 |
| Technical Communicators | Develop Help system | 3 wks | Mon 12/2/02 | Fri 12/20/02 | $0.00 |
| Technical Communicators | Review Help documentation | 3 days | Mon 12/23/02 | Wed 12/25/02 | $0.00 |
| Technical Communicators | Incorporate Help documentation feedback | 2 days | Thu 12/26/02 | Fri 12/27/02 | $0.00 |
| Technical Communicators | Develop user manuals specifications | 2 days | Thu 11/7/02 | Fri 11/8/02 | $0.00 |
| Technical Communicators | Develop user manuals | 3 wks | Mon 12/2/02 | Fri 12/20/02 | $0.00 |
| Technical Communicators | Review all user documentation | 2 days | Mon 12/23/02 | Tue 12/24/02 | $0.00 |
| Technical Communicators | Incorporate user documentation feedback | 2 days | Wed 12/25/02 | Thu 12/26/02 | $0.00 |
| | Documentation complete | 0 days | Fri 12/27/02 | Fri 12/27/02 | $0.00 |
| | Pilot | 68 days | Wed 10/23/02 | Fri 1/24/03 | $0.00 |
| Project Manager | Identify test group | 1 day | Wed 10/23/02 | Wed 10/23/02 | $0.00 |
| | Develop software delivery mechanism | 1 day | Thu 10/24/02 | Thu 10/24/02 | $0.00 |
| Deployment Team | Install/deploy software | 1 day | Thu 1/16/03 | Thu 1/16/03 | $0.00 |
| Deployment Team | Obtain user feedback | 1 wk | Fri 1/17/03 | Thu 1/23/03 | $0.00 |
| Deployment Team | Evaluate testing information | 1 day | Fri 1/24/03 | Fri 1/24/03 | $0.00 |
| | Pilot complete | 0 days | Fri 1/24/03 | Fri 1/24/03 | $0.00 |
| | Deployment | 5 days | Mon 1/27/03 | Fri 1/31/03 | $0.00 |
| Deployment Team | Determine final deployment strategy | 1 day | Mon 1/27/03 | Mon 1/27/03 | $0.00 |
| Deployment Team | Develop deployment methodology | 1 day | Tue 1/28/03 | Tue 1/28/03 | $0.00 |
| Deployment Team | Secure deployment resources | 1 day | Wed 1/29/03 | Wed 1/29/03 | $0.00 |
| Deployment Team | Train support staff | 1 day | Thu 1/30/03 | Thu 1/30/03 | $0.00 |
| Deployment Team | Deploy software | 1 day | Fri 1/31/03 | Fri 1/31/03 | $0.00 |
| | Deployment complete | 0 days | Fri 1/31/03 | Fri 1/31/03 | $0.00 |
| | Post Implementation Review | 3 days | Mon 2/3/03 | Wed 2/5/03 | $0.00 |
| Project Manager | Document lessons learned | 1 day | Mon 2/3/03 | Mon 2/3/03 | $0.00 |
| Project Manager | Distribute to team members | 1 day | Tue 2/4/03 | Tue 2/4/03 | $0.00 |
| Project Manager | Create software maintenance team | 1 day | Wed 2/5/03 | Wed 2/5/03 | $0.00 |
| | Post implementation review complete | 0 days | Wed 2/5/03 | Wed 2/5/03 | $0.00 |
| | Software development template complete | 0 days | Wed 2/5/03 | Wed 2/5/03 | $0.00 |